水泥厂施工组织设计
表 表 B.0.1 施工组织设计/ / (专项)施工方案报审表
工程名称: 宜州广驰水泥有限责任公司 2500t/d 新型干法水泥熟料生产线技改工程
致:
广西新厦工程咨询有限公司 (项目监理机构)
我方已完成
宜州广驰水泥有限责任公司 d 2500t/d 新型干法水泥熟料生产线技改工程施工组织设计/(专项)施工方案的编制和审批,,请予以审查。
附:√施工组织设计
承包单位(盖章):
广西德佳建筑工程有限公司
项目经理(签字):
日
期:
审查意见:
专业监理工程师(签字):
日
期:
审核意见:
项目监理机构(盖章):
总监理工程师(签字、加盖执业印章):
日
期:
审批意见(仅对超过一定规模的危险性较大的分部分项工程专项施工方案):
建设单位(盖章):
建设单位代表(签字):
日
期:
宜州广驰水泥有限责任公司 2500t/d 新型干法水泥熟料生产线技改工程
施工组织设计
宜州广驰水泥有限责任公司 2500t/d 新型干法水泥熟料生产线技改工程
施工方案审核、审批表
工程名称 宜州广驰水泥有限责任公司 2500t/d 新型干法水泥熟料生产线技改工程
施工单位 广西德佳建筑工程有限公司
我项目部已根据施工合同的有关规定完成了
宜州广驰水泥有限责任公司 2500t/d 新型干法水泥熟料生产线技改工程 施工组织设计
的编制,请予以审查,批准。
(施工组织设计附在表后)
编制人签名
审核部门 审核意见 审核人签名 审核日期 技术
安全
质量
总承包单位技术负责人审批意见:
总承包单位(公章)
签名:
日期:
年
月
日
宜州广驰水泥有限责任公司 2500t/d 新型干法水泥熟料生产线技改工程
目 目
录 1
编制说明及依据 ···································································································· 1 1.1
编制说明 ······································································································· 1 1.2
编制依据 ······································································································· 1 2 工程概况和工程范围 ······························································································· 1 2.1 工程总体简介 ··································································································· 1 2.2
工程范围 ······································································································· 2 2.2.1 施工范围
································································································································· 2 2.2.2 材料供应范围
························································································································· 2 2.3
气象特征及厂址条件 ······················································································· 3 2.3.1
气象特征
······························································································································· 3 2.4
工程特点及施工策划 ························································································· 3 3 施工部署 ·············································································································· 4 3.1
组织机构及专业人员设置 ··················································································· 4 3.2
工程建设目标 ·································································································· 7 3.3
施工总体安排 ·································································································· 8 3.3.1 场地规划
································································································································· 8 3.3.2 总体施工工序安排
················································································································· 9 3.3.3 主要施工工艺及机械设备选择
····························································································· 9 3.4
主要工程材料供应组织 ···················································································· 10 3.4.1 建筑工程材料供应
················································································································ 10 3.4.2 组织措施
································································································································ 10 4
施工方案及主要分项施工方法 ··············································································· 10 4.1
主要单项工程施工方法简述 ············································································· 10 4.2
关键工序的划分和管理原则 ············································································· 12 4.3
主要分项工程施工方法 ···················································································· 12 4.3.1 施工测量
······························································································································· 12 4.3.2 土方工程
······························································································································· 14 4.3.3 钢筋工程
······························································································································· 15 4.3.4 模板工程
································································································································ 17 4.3.5 脚手架工程
··························································································································· 18 4.3.6 混凝土工程
···························································································································· 19 4.3.7 大体积混凝土防裂措施
······································································································· 22 4.3.8 施工缝的处理
······················································································································· 23 4.3.9 清水混凝土施工工艺
··········································································································· 24 4.3.10 预留孔洞的施工方法
········································································································· 27 4.3.11 预埋件的施工方法
············································································································· 30 4.3.12 设备基础及二次灌浆
········································································································· 36 4.3.13 钢结构加工及安装
············································································································· 37 4.3.14 砌体工程
····························································································································· 40 4.3.15 混凝土预制构件加工
········································································································· 41
宜州广驰水泥有限责任公司 2500t/d 新型干法水泥熟料生产线技改工程
4.3.16 建筑装饰及楼地面工程
····································································································· 41 4.3.17 屋面防水工程
····················································································································· 45 4.3.18 水电安装工程
····················································································································· 46 4.4
主要单位工程施工方案 ···················································································· 51 4.4.1 烧成窑头施工方案
··············································································································· 51 4.4.2 窑中施工方案
······················································································································· 52 4.4.3 烧成窑尾施工方案
··············································································································· 53 4.4.4 原料调配站施工方案
··········································································································· 54 4.4.5 生料均化库施工方案
··········································································································· 60 4.4.6 熟料储存及汽车散装施工方案
··························································································· 62 4.4.7 石灰石预均化堆场及输送施工方案
··················································································· 63 4.4.8 原煤预均化堆场及输送施工方案
······················································································· 64 4.4.9 石灰石输送施工方案
··········································································································· 65 4.4.10 煤粉制备与输送施工方案
································································································· 66 5
施工准备 ··········································································································· 67 5.1
总体准备 ····································································································· 67 5.2
进场准备 ····································································································· 68 5.2.1 施工技术准备
························································································································ 68 5.2.2
施工现场准备
····················································································································· 69 5.2.3
工程材料准备
····················································································································· 69 5.2.4
施工机械设备准备
············································································································· 70 5.2.5
劳动力资源准备
················································································································· 70 6
劳动力计划 ········································································································ 70 6.1
劳动力计划 ·································································································· 70 6.2 劳动力组织措施 ······························································································ 72 6.3
人员培训和资格评定 ······················································································· 73 6.3.1
人员培训
····························································································································· 73 6.3.2
资格评定
····························································································································· 73 7 施工机械配备和周转工具计划 ················································································· 74 7.1
主要设备配置 ································································································ 74 7.2
周转工具计划 ······························································································· 75 8 保证工程质量的技术组织措施 ················································································· 76 8.1
质量目标 ····································································································· 76 8.2
质保体系 ····································································································· 76 8.2.1
公司质量管理体系简介
····································································································· 76 8.2.2 本工程质量保证体系及运行措施
························································································ 77 8.3
质量标准 ····································································································· 79 8.4
质量管理措施 ······························································································· 81 8.4.1
质量管理措施概述
············································································································· 81 8.4.2 施工各阶段质量管理的主要工作
······················································································· 83 8.4.3 工序质量的控制措施
········································································································· 86 8.4.4 质量控制点
···························································································································· 89
宜州广驰水泥有限责任公司 2500t/d 新型干法水泥熟料生产线技改工程
8.4.5 确保施工技术资料真实、完整的措施
················································································ 91 8.5
质量通病的控制措施 ······················································································ 91 8.6
本工程质量保证计划 ······················································································ 94 9
保证工期的技术组织措施 ····················································································· 94 9.1
工期保证的技术措施 ······················································································· 94 9.2
工期保证的组织措施 ······················································································· 95 9.3
经济合同措施 ······························································································· 96 9.4
节假日保勤措施 ···························································································· 96 9.5
冬期施工保证措施 ························································································· 97 10
确保安全施工的技术组织措施 ·············································································· 98 10.2.2
安全管理人员安排及职责
····························································································· 100 10.2.3
安全管理制度
················································································································· 103 10.2.4
安全管理的实施
············································································································· 104 10.3
安全生产控制措施 ······················································································· 108 10.3.1
制定项目安全保证计划
································································································· 108 10.3.2
安全保证计划的实施
····································································································· 108 10.3.3
安全生产保证措施
········································································································· 109 10.3.4
安全检查验收工作
·········································································································· 113 10.3.5
安全隐患和安全事故处理
······························································································ 114 10.3.6
施工现场安全经费管理
·································································································· 115 11 确保文明施工的技术措施 ····················································································· 115 11.1
文明施工管理目标 ························································································ 115 11.2
文明施工管理制度和措施 ··············································································· 115 11.2.1
建立健全现场文明施工管理组织机构及职责
······························································ 115 11.2.2
文明施工实施方案及措施
······························································································ 116 11.2.3
环保措施
·························································································································· 119 11.2.4 文明施工考核及管理办法
······························································································· 120 12 施工总进度计划 ································································································· 121 12.1 工期目标 ···································································································· 121 12.2
主要工程二级计划进度 ·················································································· 122 12.3
图纸交付进度要求 ························································································ 122 12.4
施工进度计划图 ··························································································· 122 13 施工平面布置 ···································································································· 124 13.1
平面布置原则 ······························································································ 124 13.2 平面布置依据 ······························································································ 124 13.3
临建设施布置及用地 ···················································································· 125 13.3.1 生活设施布置
··················································································································· 125 13.3.2 生产设施布置
···················································································································· 125 13.3.3 道路布置
··························································································································· 126 13.3.4 水电布置
··························································································································· 126 13.3.5 施工平面布置图
··············································································································· 126
宜州广驰水泥有限责任公司 2500t/d 新型干法水泥熟料生产线技改工程
14
降低成本、提高质量的合理化建议 ······································································· 128 15
施工管理 ········································································································ 128 15.1
施工管理制度 ····························································································· 128 15.2
施工计划管理 ····························································································· 129 15.3
劳动力计划管理 ·························································································· 132 15.4
物资管理 ··································································································· 133 15.5
机械设备管理 ····························································································· 136 15.6
施工技术管理 ····························································································· 137 15.7
质量管理 ··································································································· 138 15.7.1
质量管理的基本内容及要求
························································································· 138 15.7.2
编制项目质量计划
········································································································· 138 15.7.3
质量计划的内容
············································································································· 139 15.7.4
质量计划的实施
····...
本栏目阅读排行
栏目最新
- 1在农民收入调查工作动员培训会上讲话
- 22024年领导干部政治素质自评材料(完整)
- 3公司党委党建工作总结报告【完整版】
- 42024年主题教育党建调研开展情况总结
- 52024年度区妇联关于党建工作述职报告(完整)
- 6关于加强企业人才队伍建设调研与思考(完整文档)
- 72024县党员干部抓基层党建工作述职报告
- 8第二批主题教育研讨发言:时刻“以民为本”,听“实言实语”,办实事好事
- 92024关于党员干部法治信仰情况调研报告(2024年)
- 10局网络安全工作责任制落实自查报告(全文)
- 11XX国企分管领导关于党建设引领企业高质量发展研讨发言(范文推荐)
- 122024年第二批主题教育专题读书班研讨发言提纲(6)【完整版】